Back to News

UK's £5bn Project Gigabit Hits 40% Completion - What It Means for Businesses Still Waiting for Fibre

UK's £5bn Project Gigabit Hits 40% Completion - What It Means for Businesses Still Waiting for Fibre

The latest monthly progress figures from Building Digital UK (BDUK) show that the government’s £5bn Project Gigabit scheme has now delivered a gigabit–capable connection to 340,880 of the 861,890 premises it has under contract — a completion rate of 40%, up from 318,000 premises, or 37%, in September 2026. On the national numbers that is steady progress. Under the national numbers it is anything but. One Openreach contract covering North Herefordshire, North Wales, Shropshire and South West Wales is just 7% complete and added no premises at all this month. A Wildanet contract in Central Cornwall has finished. One Openreach contract in Devon and North Somerset went backwards.

For a UK business, the national percentage is close to meaningless. What matters is the contract that covers your postcode, its supplier, and how it is actually performing — and on today’s figures, 24 October 2026, the gap between the best and worst contracts is the gap between a business that can plan around fibre arriving next quarter and one that may still be waiting years from now. For organisations in the slower intervention areas, which BDUK’s figures place largely in Wales, Scotland, Shropshire and parts of South West England, the sensible reading of this month’s update is not “fibre is coming”. It is “design the network you can rely on today, and treat fibre as an upgrade when it lands”.

340,880
Premises connected under Project Gigabit contracts by October 2026, out of 861,890 contracted — up 22,880 on September’s 318,000
40%
National completion across all Project Gigabit contracts, up from 37% a month earlier. The spread between individual contracts runs from 7% to 100%
7%
Completion of Openreach’s CO3 contract covering North Herefordshire, North Wales, Shropshire and South West Wales — with zero premises added this month
2032
Target date for c.99% nationwide gigabit coverage. Ofcom puts commercial coverage at 91% today, forecast to reach 95% by January 2029

What BDUK’s October update actually shows

Project Gigabit exists to reach the premises that the commercial market will not reach on its own — the “final 10–20%” of the UK, typically rural, remote or otherwise expensive to build to. Commercial operators have already taken gigabit–capable networks to around 91% of premises, according to Ofcom, and the regulator forecasts that commercial build alone, independent of this scheme, will reach 95% by January 2029. The subsidy programme is aimed at what lies beyond that commercial horizon, with a goal of roughly 99% gigabit coverage nationwide by 2032. BDUK lets that work out as a set of regional contracts, each awarded to a single supplier, and publishes each contract’s progress monthly.

This month’s national total of 340,880 connected premises against 861,890 contracted represents 22,880 premises added in a month. If that pace held exactly — and the contract–level data suggests strongly that it will not hold evenly — the remaining 521,010 premises would take the best part of two more years to reach. That is simple arithmetic rather than a forecast, and it is useful mainly as a sense of scale: even on the national average, the programme is closer to the start of its work than the end.

The more instructive part of the update is the contract–by–contract spread. Wildanet’s Central Cornwall contract has reached 100%. CityFibre’s contracts in Cambridgeshire and in Bedfordshire, Northamptonshire and Milton Keynes are each at 82%. At the other end, Openreach’s CO3 contract — North Herefordshire, North Wales, Shropshire and South West Wales — stands at 7% and added nothing this month, while Openreach’s CO4 contract covering South Devon, Mid Devon and North Somerset recorded a net change of −10 premises, attributed to a pending data revision. Contracts in parts of Wales, Scotland, Shropshire and South West England remain under 20% complete. The same programme, the same month, and a range of outcomes wide enough that the national figure describes almost nobody’s actual position.

A fibre date is a plan, not a connection — and plans in this programme slip

The commonest connectivity mistake a UK SME in a rural or semi–rural area makes is to defer every network decision until “the fibre arrives”. It feels prudent: why invest in a backup line or a better router when a gigabit service is supposedly on its way? The October figures show why it is not prudent. A contract can sit at single–digit completion with no premises added in a month. A contract’s reported total can go down as data is revised. A planned build date published for a postcode is the supplier’s current intention, not a commitment with a penalty attached to your business if it moves. Meanwhile the business is running on whatever it has today — often a single copper–based line, frequently with no failover, carrying voice, card payments, cloud applications and backups at once. If that line fails tomorrow, the fibre date does not help. The risk to manage is the connection you actually have, for however long you actually have it.

How Project Gigabit got here, and where it is heading

The programme’s headline dates stretch to the next decade. The dates that matter for an individual business are the contract milestones in its own region, and those are published monthly.

2021 — £5bn Project Gigabit is launched
The government commits £5bn to subsidise gigabit–capable broadband for the hardest–to–reach final 10–20% of UK premises, delivered by BDUK through regional contracts let to individual suppliers — Openreach alongside alternative network operators.
September 2026 — 318,000 premises connected (37%)
BDUK’s September figures put the programme at 318,000 connected premises across its contracts. Commercial build, entirely separate from the scheme, has meanwhile reached around 91% of UK premises according to Ofcom.
October 2026 — 340,880 of 861,890 premises connected (40%)
The monthly update adds 22,880 premises nationally and lifts completion to 40%. The headline hides a spread from 7% to 100% between individual contracts.
October 2026 — Wildanet finishes Central Cornwall; CityFibre reaches 82%
Wildanet’s Central Cornwall contract reaches 100% completion. CityFibre’s Cambridgeshire contract and its Bedfordshire, Northamptonshire and Milton Keynes contract each stand at 82% — evidence that delivery at pace is achievable within the programme.
October 2026 — Openreach CO3 stalls at 7%
Openreach’s CO3 contract, spanning North Herefordshire, North Wales, Shropshire and South West Wales, adds zero premises in the month and remains 7% complete. Other contracts in Wales, Scotland, Shropshire and parts of South West England remain below 20%.
October 2026 — Openreach CO4 records a net fall of 10 premises
The South Devon, Mid Devon and North Somerset contract goes backwards on paper, with the change attributed to a pending data revision. A small number, but a clear signal that month–to–month figures are volatile and do not move in a straight line.
January 2029 — Commercial gigabit coverage forecast to reach 95%
Ofcom’s forecast for commercial build alone, not reliant on Project Gigabit subsidy. The gap between that 95% and the 99% target is the territory the scheme exists to cover — and where the slowest contracts sit.
2032 — Target for c.99% nationwide gigabit coverage
The programme’s end goal. For a business in a contract area still under 20% complete in late 2026, this is the honest outer bound to plan against — not because the build will necessarily take that long, but because nothing in the published data guarantees it will not.

The same programme, very different results

The bars below set the national completion figures alongside the individual contracts named in BDUK’s October update. The spread is the story: a business in Central Cornwall and a business in Shropshire are covered by the same scheme and are in completely different positions.

Wildanet — Central Cornwall
100%
CityFibre — Cambridgeshire
82%
CityFibre — Bedfordshire, Northamptonshire & Milton Keynes
82%
Project Gigabit national total — October 2026
40%
Project Gigabit national total — September 2026
37%
Lagging contracts in Wales, Scotland, Shropshire & South West England
<20%
Openreach CO3 — N Herefordshire, N Wales, Shropshire, SW Wales
7%

Two things follow from that chart. The first is that delivery speed in this programme is a property of the individual contract, not of the scheme. The contracts at 82% and 100% demonstrate that the build can be done at pace in subsidised areas; the contracts below 20% demonstrate that it is not being done at pace everywhere. A business cannot infer its own timeline from the national figure, from a neighbouring county, or from what it read about the programme last year. It has to look at its own contract.

The second is that the lagging contracts are geographically concentrated in places where alternatives are also thinner. Rural Wales, Shropshire, parts of Scotland and the South West are not just where subsidised fibre is slowest; they are also where mobile coverage can be patchy, where a second fixed–line provider is less likely to be available, and where an engineer visit after a fault takes longer to arrange. A business there carries more connectivity risk on today’s infrastructure and has fewer easy routes to reduce it, which is exactly why it cannot afford to wait for a fibre date before thinking about resilience.

Most of the work is still ahead

Five years into a programme with a 2032 end date, the national figure is a fair indication of where things stand overall — and of how much of the build is still to come in the places that are hardest to reach.

40%
Share of the 861,890 premises contracted under Project Gigabit that had received a gigabit–capable connection by October 2026 — 340,880 premises. The remaining 521,010 are, by design, the most expensive and difficult in the programme to reach

It is tempting to read 40% as “well under way”. A more useful reading is that the programme is selected towards difficulty: Project Gigabit only covers premises the commercial market declined to build to, and within that group, the premises still waiting are the ones that were not easy enough to connect first. In practical terms that means long rural spans, difficult terrain, wayleaves across private land, poles that need replacing and duct that does not exist. The final stretch of any build of this kind tends to be slower per premises than the opening stretch, not faster, and month–to–month totals that occasionally go backwards as records are revised are what that complexity looks like in the data.

For the businesses inside that remaining 60%, the shape of the next few years is therefore uncertain in a specific way. Fibre will very probably arrive. The date on which it arrives, and how firm any published date turns out to be, is not something the business can control or rely on. That is a planning problem rather than a technology problem, and it has a well–understood answer: build resilience into the connection you have now, choose equipment that will carry over when fibre lands, and avoid long contracts that lock you into today’s product past the point where something better becomes available.

There is a timing collision to keep in mind as well. The national copper switch–off completes on 31 January 2027, and businesses in areas without fibre are generally moving from analogue lines to SOGEA–based broadband with hosted voice over the same copper infrastructure. That is a perfectly sound interim step, but it concentrates more on a single circuit than before: voice, card payments, alarm signalling and every cloud application now depend on one broadband line that, in a lagging intervention area, may be a long copper run with a modest speed and no alternative path. The switch–off makes resilience more important in exactly the places where the fibre build is slowest.

Where waiting on a single fibre date leaves a business exposed

The list below reflects the connectivity weak points most commonly found in UK SMEs located in slower Project Gigabit areas, with badges indicating how much attention each typically needs.

Connectivity risk for a business still waiting for fibre
A single fixed line with no backup path of any kind High
Voice, payments and alarm signalling all riding on that same circuit after the copper switch–off High
Cloud backups that cannot complete overnight on the available upload speed High
No measured mobile signal survey for the site before relying on 4G or 5G as failover Mid
A consumer–grade router with no multi–WAN or automatic failover capability Mid
A long broadband contract that will outlast the arrival of fibre Mid
No record of which BDUK contract and supplier cover the premises Mid
Unknown fault repair commitment on the current line Low

The pattern across the top three rows is concentration. Each one is fine in isolation; together they describe a business whose voice, revenue, safety signalling and data protection all fail at the same moment, for the same reason, with no way round it. That is the situation in which a fibre date becomes a liability rather than a plan, because it gives everyone a reason to defer the work that would have broken the dependency. The backup point deserves particular attention: on a slow upload link, a cloud backup that never quite finishes is indistinguishable, from the dashboard, from one that does — until the day it is needed.

What resilience costs while you wait

The bands below are indicative planning figures for UK businesses adding resilience to an existing connection pending fibre, covering hardware, installation and typical monthly service costs. They are not quotes. The variable that moves them most is the quality of mobile signal at the site, which is why a proper survey belongs at the start rather than the end.

Business size Typical approach Indicative cost What it changes
Micro business, 1 – 5 staff, single site Business router with automatic 4G/5G failover, data SIM, external antenna where signal is weak, battery backup for router and voice £250 – £700 setup, then £15 – £40 a month A line fault becomes a slower afternoon rather than a closed business; card payments and calls keep working
Small business, 6 – 25 staff, one site Multi–WAN firewall combining the fixed line with a 4G/5G circuit, traffic prioritisation for voice, signal survey, monitored failover £900 – £2,500 setup, then £40 – £120 a month Automatic failover in seconds, voice protected under load, and an alert when the primary line drops rather than a phone call from a customer
Mid–sized business, 26 – 100 staff, or several rural sites SD–WAN across sites, bonded or dual–carrier mobile, application–aware routing, centrally managed policy £3,000 – £12,000 setup, then £150 – £600 a month Every site with two independent paths and consistent behaviour across the estate, ready to absorb fibre as each site gets it
Business with heavy, critical bandwidth needs Leased line where economically viable, with mobile or satellite backup; excess construction charges assessed case by case From £250 a month plus any construction charges Dedicated, contracted service with a fault repair commitment, independent of the Project Gigabit timetable

Two points on reading that table. First, almost nothing in the first three rows is wasted when fibre arrives: a multi–WAN firewall or SD–WAN appliance simply gains a faster primary link, and the mobile circuit becomes the backup it always should have been. Resilience spent now is not a bet against the rollout; it is equipment the business needs either way. Second, the leased–line row is the only route that removes dependence on the programme altogether, and for most small rural businesses it will not be economic — which is precisely why the interim approaches above matter so much.

Two ways to handle a fibre date you cannot control

Waiting for the fibre

What many rural and semi–rural SMEs do today

  • Network decisions deferred until a gigabit service arrives, on a date nobody has confirmed in writing
  • A single fixed line carrying voice, payments, cloud applications and backups, with no alternative path
  • The national 40% figure, or a neighbour’s experience, used as a proxy for the business’s own timeline
  • Consumer–grade router and no failover, because “it will all change when fibre comes”
  • A line fault means a closed business until an engineer visit can be arranged
  • Cloud backups silently incomplete on a slow upload link
  • A long contract signed on today’s product that will outlast the arrival of something better

Designing for the connection you have

Where Cloudswitched takes you

  • The specific BDUK contract, supplier and current completion figure for your premises established and tracked monthly
  • A second, independent path — typically 4G/5G — with automatic failover, sized from a measured signal survey
  • Multi–WAN or SD–WAN equipment that carries straight over when fibre lands
  • Voice prioritised and protected, with battery backup so calls survive a power cut
  • Backups scheduled and verified against the bandwidth you actually have
  • Contract terms aligned to the likely fibre window, so you can move when it becomes available
  • Fibre treated as an upgrade to a resilient network, not as the thing the network is waiting for

The difference between those columns is not how much is spent; it is whether the business’s continuity depends on someone else’s build programme. Every item on the right–hand side can be done today, at the address the business currently occupies, on the infrastructure that is currently there — and every one of them keeps its value after the fibre arrives.

34
Indicative connectivity resilience score, out of 100, for a typical UK SME in a Project Gigabit area still below 20% complete — one running a single copper–based broadband line with no failover, carrying voice and payments over it, and planning around a fibre date that has not been confirmed
Find your contract before you trust your date

BDUK publishes its Project Gigabit contract list and each contract’s completion percentage every month, which means you can see the delivery record of the specific contract covering your premises rather than relying on the national total. Identify which contract and supplier cover your area, note its current completion figure and how many premises it added in the last month, and check it again each month. A contract adding thousands of premises a month and sitting above 80% is a reasonable basis for short–term planning. A contract in single digits, or one that added nothing last month, is not — and if that is yours, the decision about backup connectivity should be made now rather than after the next line fault. Ask your current provider in writing what fault repair commitment applies to your line today, too: it tells you how long a single failure could actually last.

Why this is a planning question, not just a broadband one

It is easy to file Project Gigabit under infrastructure news — something that happens to a region rather than something a business decides. That framing is understandable and it is the reason so many rural businesses end up with networks designed around an event rather than around their own operations. The more accurate framing is that connectivity is now the single dependency underneath almost everything an SME does: telephony after the copper switch–off, card payments, Microsoft 365 or Google Workspace, line–of–business applications hosted in the cloud, backups, remote access and security updates. A business that has moved all of that to the cloud has also moved its continuity risk onto its broadband line, whether or not anyone noticed it happening.

Seen that way, a fibre rollout date is an input to a technology roadmap, alongside contract renewals, hardware refresh cycles and the copper switch–off. It belongs in the same plan as those things, with the same discipline: what is the dependency, what is its current state, what is the realistic window for change, and what is the fallback if the window slips. That is the kind of question a virtual CIO or a strategic IT partner asks routinely, and it is the question that converts this month’s BDUK update from a news item into a decision.

It also shapes procurement. A business that expects fibre within twelve months should avoid signing a three–year term on its current broadband product, and should buy routing and firewall equipment that will handle a gigabit primary link when it arrives. A business whose contract is in single digits should do the opposite of waiting: invest in a resilient interim design now, on the assumption that it will be in service for some years, and treat any earlier fibre arrival as a bonus. Both are rational. What is not rational is the common middle position — doing nothing because fibre is “coming”, with no idea from which contract, which supplier or how fast that contract is actually moving.

The story at a glance

Item Detail
The programme Project Gigabit, a £5bn government scheme delivered by BDUK through regional supplier contracts
Who it is for The hardest–to–reach “final 10–20%” of UK premises that commercial build will not reach on its own
October 2026 progress 340,880 of 861,890 contracted premises connected — 40% complete
September 2026 progress 318,000 premises connected — 37% complete
Added this month 22,880 premises nationally
Fastest contracts named Wildanet Central Cornwall at 100%; CityFibre Cambridgeshire and Bedfordshire, Northamptonshire & Milton Keynes each at 82%
Slowest contract named Openreach CO3 — North Herefordshire, North Wales, Shropshire, South West Wales — at 7% with zero premises added this month
A contract that went backwards Openreach CO4 — South Devon, Mid Devon, North Somerset — net change of −10 premises, attributed to pending data revision
Lagging regions Contracts in parts of Wales, Scotland, Shropshire and South West England remain under 20% complete
Commercial coverage today 91% of UK premises gigabit–capable, according to Ofcom
Commercial forecast 95% by January 2029, independent of Project Gigabit
Programme target c.99% nationwide gigabit coverage by 2032
Where to check your area BDUK’s monthly contract list and completion percentages
Interim resilience options 4G/5G backup circuits, multi–WAN failover, SD–WAN, battery backup for voice; leased lines where viable
The one action this month Identify the BDUK contract covering your premises, read its actual completion figure, and decide on backup connectivity on that basis rather than on the national total

This story connects to several we have covered in the past week. The danger of having only one path to fail over to was demonstrated at national scale by Google Cloud’s UK outage, which knocked out banks and courts because there is only one UK region to fail over to — the same single–path logic, applied to a data centre rather than a rural broadband line. A business whose backups run over a slow upload link should also read ConnectWise suspending its cloud backup after M365 credential theft, which is a reminder that backup resilience depends on both the provider and the path to it. And for businesses on thin connections where large updates are already a strain, our analysis of security patches breaking ten times more often and the “patch or go offline” warning over critical PHP flaws both show why the ability to download, test and roll back updates promptly is itself a connectivity question.

Is your business running on a fibre date or on a resilient connection?

Cloudswitched designs business connectivity around the infrastructure you actually have — establishing which Project Gigabit contract covers your premises and how it is really performing, surveying mobile signal before relying on it, and specifying 4G/5G failover, multi–WAN or SD–WAN equipment that keeps calls, payments and cloud applications working through a line fault and carries straight over when fibre arrives. If you are in an area where the build is slow, the right time to stop depending on a single line is before it next fails.

Talk to us about Business Connectivity

Frequently asked questions

What is Project Gigabit, and does it cover my business?
Project Gigabit is the government’s £5bn programme, run by Building Digital UK, to subsidise gigabit–capable broadband in the hardest–to–reach final 10–20% of UK premises — the places commercial operators are not expected to build to on their own. It is delivered through regional contracts, each awarded to a single supplier. Whether it covers your business depends on whether your premises fall inside a contracted intervention area. If you are in a town or city already served commercially, you are probably not in scope; if you are rural or semi–rural and have no gigabit option today, there is a reasonable chance you are, and BDUK’s monthly contract list is the place to check.
The programme is 40% complete. Does that mean I am 40% of the way to fibre?
No, and this is the most important point in the October figures. The 40% is a national average across all contracts — 340,880 of 861,890 premises connected. Individual contracts range from 7% to 100%. Wildanet’s Central Cornwall contract has finished, CityFibre’s contracts in Cambridgeshire and in Bedfordshire, Northamptonshire and Milton Keynes are at 82%, and Openreach’s CO3 contract in North Herefordshire, North Wales, Shropshire and South West Wales is at 7% with no premises added this month. Your position depends entirely on which contract covers your premises and how that contract is performing.
How do I find out which contract covers my premises?
BDUK publishes its Project Gigabit contract list and each contract’s completion percentage monthly, which lets you see the delivery record of the contract for your region rather than relying on the national total. Note the supplier, the completion figure and how many premises the contract added in the latest month, and recheck it each month. Your current broadband provider and the suppliers’ own availability checkers can also indicate whether your specific address is in a planned build. Treat any published build date as the supplier’s current intention rather than a commitment — the October figures show contracts can stall, and in one case report a net fall, from month to month.
Why did one contract go backwards?
Openreach’s CO4 contract, covering South Devon, Mid Devon and North Somerset, recorded a net change of minus ten premises in October, attributed to a pending data revision. A figure moving down because records are being corrected is not unusual in a programme of this size, and ten premises is a small number. The significance for a business is not the size of the change but what it says about the data: monthly figures are volatile, they do not move in a straight line, and a single month’s progress, good or bad, is a weak basis for predicting when an individual address will be connected.
If fibre is on the way, why should we spend money on backup connectivity now?
Because the business is running on its current connection every day until fibre arrives, and in a contract area still under 20% complete that could be a long time. The other reason is that resilience equipment is not wasted when fibre lands. A multi–WAN firewall or SD–WAN appliance simply gains a faster primary link, and the 4G or 5G circuit becomes the backup that a business on fibre should also have. The spend is on equipment you need in either future. The thing to avoid is the opposite — a long contract on today’s broadband product that will outlast the arrival of fibre, which is a commitment worth checking before you renew.
Is 4G or 5G a realistic backup in a rural area?
Often, but it should be measured rather than assumed. The regions with the slowest Project Gigabit contracts also tend to have patchier mobile coverage, and coverage maps describe outdoor signal rather than what reaches a router inside a stone building. A proper signal survey at the site, testing more than one network, tells you whether a mobile backup will carry voice and essential applications. Where indoor signal is weak, an external antenna frequently makes the difference. Where one network is poor, a router that can use a second carrier adds another layer. In the hardest locations, satellite services are worth considering as a backup path.
What is the difference between multi–WAN failover and SD–WAN?
Multi–WAN failover is the simpler idea: a router or firewall with two or more internet connections that switches traffic to the backup automatically when the primary line fails, and usually lets you prioritise important traffic such as voice. It suits most single–site small businesses. SD–WAN goes further, steering individual applications across the available links based on live performance, combining links where useful, and applying a consistent policy across several sites from a central console. It suits businesses with multiple locations or applications that are sensitive to latency and packet loss. Both carry straight over when fibre arrives.
How does the copper switch–off interact with waiting for fibre?
The national PSTN switch–off completes on 31 January 2027, and in areas without fibre the usual migration is to SOGEA broadband with hosted voice running over the same copper infrastructure. That is a sound interim step, but it puts voice, card payments, alarm signalling and cloud applications on one broadband circuit, and analogue lines used to keep working in a power cut where digital voice does not. For a business in a slow intervention area, the migration and the resilience design belong in the same project: a backup path, battery backup for the router and handsets, and a clear plan for what happens to payments and alarms during an outage.
Our cloud backups seem fine. Why would the connection matter?
Because on a slow upload link a backup can fall behind without anyone noticing. If a nightly job needs more time than the available upload speed allows, it may run into the working day, compete with live traffic, or quietly leave each run incomplete, and summary dashboards do not always make that obvious. Check the actual completion times and sizes of recent backup jobs against your upload speed, confirm that a full restore of a critical system has been tested recently, and consider local backup alongside cloud storage so that recovery does not depend on downloading everything over the same thin line. Restore speed matters as much as backup speed.
Should we pay for a leased line instead of waiting?
For some businesses, yes. A leased line is a dedicated, contracted connection with a fault repair commitment, entirely independent of the Project Gigabit timetable, and for a business whose operations cannot tolerate an outage it may be the right answer. In rural areas the barrier is usually cost: installation can attract excess construction charges where new duct or cabling is needed, and those vary widely from site to site. Get a site–specific quote rather than a list price, compare it honestly with a resilient interim design using your existing line plus a mobile backup, and weigh both against how much an outage actually costs your business per day.

Fibre will arrive. Your business needs to work until it does.

The October figures show a programme moving forward nationally and standing still in places, with no way for an individual business to speed up its own contract. What a business can control is how much of its operation depends on a single line in the meantime. Cloudswitched builds resilient connectivity for UK businesses in every kind of location — signal surveys, 4G/5G failover, multi–WAN and SD–WAN, voice and payment continuity through the copper switch–off, and equipment that carries straight over when the gigabit service finally lands. Start by finding out which contract covers you, and design from there.

Talk to us about Business Connectivity
Tags:ConnectivityNetworkingIT SupportVirtual CIO
Cloudswitched

London-based managed IT services provider offering support, cloud solutions and cybersecurity for SMEs.

Cloudswitched Service

Business Connectivity & Network Security

Business broadband, leased lines and secure network infrastructure for UK businesses

More about this service
CloudswitchedBusiness Connectivity & Network Security
020 3004 3450
Insights & guides

Latest from our blog

Structured Data and Schema Markup: A UK Business Guide to Winning Rich Results in Google Search in 2026
SEO5 Nov 2026

Structured Data and Schema Markup

Schema markup is structured code added to web pages that describes their content in a standard vocabulary search engines understand: this page is a product...

Read article
Website Redesign Planning: A UK Business Guide to Avoiding the Mistakes That Tank SEO Rankings During a Rebuild in 2026
Web Development4 Nov 2026

Website Redesign Planning

Treating website redesign SEO as an afterthought is the most reliable way for a UK business to lose the organic traffic it spent years building. The pattern is...

Read article
Virtual CIO Onboarding: A UK Business Guide to What the First 90 Days Should Actually Look Like in 2026
Virtual CIO3 Nov 2026

Virtual CIO Onboarding

Good virtual CIO onboarding looks, from the outside, surprisingly unglamorous. Many UK businesses sign a virtual CIO contract expecting a strategy presentation...

Read article
Network Capacity Planning: A UK Business Guide to Forecasting Growth Before Your Network Becomes the Bottleneck in 2026
Network Admin1 Nov 2026

Network Capacity Planning

Network capacity planning is the practice of knowing how much headroom each part of your network has, forecasting when growth will use it up, and acting before...

Read article
Office Downsizing and Consolidation: A UK Business Guide to Moving to a Smaller Office Without Losing IT Capability in 2026
IT Office Moves31 Oct 2026

Office Downsizing and Consolidation

Planning office downsizing IT is a different exercise from planning a normal office move, and treating it as a smaller version of one is where most problems...

Read article
Microsoft 365 Copilot Adoption: A UK Business Guide to Why Most Deployments Fail to Change How People Work in 2026
Microsoft 365 Copilot30 Oct 2026

Microsoft 365 Copilot Adoption

A workable Copilot adoption strategy starts from an uncomfortable fact: buying Microsoft 365 Copilot licences does not change how anyone works. The pattern in...

Read article
Microsoft 365 Copilot ROI: How UK Businesses Are Measuring Productivity Gains in 2026
Microsoft 365 Copilot29 Oct 2026

Microsoft 365 Copilot ROI

Most UK organisations that bought Copilot in 2024 and 2025 have reached their first or second renewal, and the question in the room has changed. Nobody is...

Read article
Penetration Testing for Web Applications: A UK Business Guide to OWASP Top 10 Testing and What a Web App Pen Test Actually Covers in 2026
Penetration Testing28 Oct 2026

Penetration Testing for Web Applications

Web application penetration testing examines the software your customers, staff and partners actually use your portal, platform, booking system or API to find...

Read article
Backup Encryption: A UK Business Guide to Protecting Backup Data at Rest and in Transit Without Locking Yourself Out in 2026
Cloud Backup27 Oct 2026

Backup Encryption

Backup encryption at rest and in transit is now standard across almost every backup product, and most UK businesses assume their backups are protected because...

Read article
Private Connectivity to Azure and AWS: A UK Business Guide to ExpressRoute and Direct Connect vs Public Internet VPN in 2026
Cloud Networking26 Oct 2026

Private Connectivity to Azure and AWS

Private cloud connectivity means linking your offices or data centre to Azure or AWS over a dedicated circuit Microsoft ExpressRoute or AWS Direct Connect...

Read article
Technology stack

Built on technology you can trust.

We design, run and secure your IT on proven, industry-leading platforms, including Microsoft 365 and Azure, Cisco Meraki, Cloudflare, AWS, BitDefender and SolarWinds, so your business stays secure, scalable and reliable.

  • SolarWinds
  • Cloudflare
  • BitDefender
  • AWS
  • Hono
  • SolarWinds
  • Cloudflare
  • BitDefender
  • AWS
  • Hono
  • Opus
  • Office 365
  • Microsoft
  • Cisco Meraki
  • Microsoft Azure
  • SolarWinds
  • Opus
  • Office 365
  • Microsoft
  • Cisco Meraki
  • Microsoft Azure
  • SolarWinds

Enquiry Received!

Thank you for getting in touch. A member of our team will review your enquiry and get back to you within 24 hours.