Free Tool
Office Move Timeline Planner
Generate a week-by-week IT relocation timeline tailored to your office size, infrastructure complexity, and move date.
Enter Your Details
Typical IT Move Timeline by Office Size
| Phase | Small (<20) | Medium (20–50) | Large (50–100) | Enterprise (100+) |
|---|---|---|---|---|
| Assessment & Planning | 1 week | 1–2 weeks | 2–3 weeks | 3–4 weeks |
| ISP & Cabling Orders | Week 1 | Week 2 | Week 3 | Week 4 |
| Infrastructure Prep | 1 week | 2–3 weeks | 3–4 weeks | 4–6 weeks |
| Pre-Move Setup & Testing | 1 week | 1–2 weeks | 2–3 weeks | 2–3 weeks |
| Move Weekend | 1 day | 1–2 days | 1 weekend | Phased weekends |
| Post-Move Support | 1 week | 1–2 weeks | 2 weeks | 2–4 weeks |
| Total Lead Time | 4–6 weeks | 6–10 weeks | 10–14 weeks | 14–20 weeks |
On-premise setups add approximately 2–4 weeks to total lead time. ISP lead times in the UK can be 30–60+ working days. Complex infrastructure adds further time for hardware staging and testing. Learn more about our IT office move service