Office Move Timeline Planner

Generate a week-by-week IT relocation timeline tailored to your office size, infrastructure complexity, and move date.

Enter Your Details

Typical IT Move Timeline by Office Size

PhaseSmall (<20)Medium (20–50)Large (50–100)Enterprise (100+)
Assessment & Planning1 week1–2 weeks2–3 weeks3–4 weeks
ISP & Cabling OrdersWeek 1Week 2Week 3Week 4
Infrastructure Prep1 week2–3 weeks3–4 weeks4–6 weeks
Pre-Move Setup & Testing1 week1–2 weeks2–3 weeks2–3 weeks
Move Weekend1 day1–2 days1 weekendPhased weekends
Post-Move Support1 week1–2 weeks2 weeks2–4 weeks
Total Lead Time4–6 weeks6–10 weeks10–14 weeks14–20 weeks

On-premise setups add approximately 2–4 weeks to total lead time. ISP lead times in the UK can be 30–60+ working days. Complex infrastructure adds further time for hardware staging and testing. Learn more about our IT office move service